We have reached another important milestone in the construction of the Diamond Foundry plant in Trujillo, the arrival of the two 45/20kV 25-30MVA power transformers for the 1st phase of its substation, from the Hitachi factory in Turkey.
With these transformers, we will supply the plant's general services and its first 9 production lines, with our sights set on 2027, when we hope to commission the 2nd phase of the substation, with the assembly of two 132/20kV 70-80MVA transformers, which will supply the entire plant, which will then have a total of 24 production lines.
The construction of this substation and its subsequent commissioning will represent for ARRAM the consolidation of this type of installation as an important part of our portfolio of services.